LEARNING OUTCOMES
- ILO 1: Students can explain the nature of production in construction
- ILO 2: Students can compare and contrast the similarities and differences of different production planning and control methods (CPM, LBMS, Takt, Last Planner System)
- ILO 3: Students can calculate the production system cost of a schedule
- ILO 4: Students can discuss variability related to production and how to mitigate variability
- ILO 5: Students can discuss flows and waste in construction
- ILO 6: Students can discuss how digital tools can support production planning and control
- ILO 7: Students can plan a location-based schedule of a real project
- ILO 8: Students can make production control decisions based on the schedule
- ILO 9: Students can analyze the quality of a location-based schedule
- ILO 10: Students can collaborate in multi-disciplinary teams
Credits: 5
Schedule: 26.02.2025 - 11.04.2025
Teacher in charge (valid for whole curriculum period):
Teacher in charge (applies in this implementation): Olli Seppänen
Contact information for the course (applies in this implementation):
CEFR level (valid for whole curriculum period):
Language of instruction and studies (applies in this implementation):
Teaching language: English. Languages of study attainment: English
CONTENT, ASSESSMENT AND WORKLOAD
Content
valid for whole curriculum period:
The course focuses on production planning and control of construction projects. In addition to interactive lectures, team group work develop skills related to production planning and control. The lecture content is available in videos. The exercises are based on practical construction case examples.
Assessment Methods and Criteria
valid for whole curriculum period:
Production planning and control assignments 25%
Participation during lectures and MyCourses discussions 25% (remote participants will substitute presence with additional MyCourses participation)
Final exam: 50%
Workload
valid for whole curriculum period:
Workload in total 135 hours:
- Lectures: 24 h (8x1,5=12 h contact time, 12 h study time)
- Flipped classroom: 14 h (reading and preparation)
- Production Planning exercise: 24 h (2*2h computer tutorials, 20 hours on own time)
- Production Control game: 12 h (2 h tutorial, 10 hours on own time)
- Weekly reading assignment: 6 h
- Weekly participation on MyCourses discussions 6 h (6x1 h)
- Evaluation of other group s project work: 10 h
- Exam preparation: 30 h
Exam: 3 h
DETAILS
Study Material
valid for whole curriculum period:
Kenley,R & Seppänen, O 2010. Location-Based Management for Construction: Planning, Scheduling and Control. Spon Press: London and New York. eISBN-13: 9780203030417 (selected chapters) - available as e-book in the library
Additionally academic journal and conference articles. These will be introduced during the course
Substitutes for Courses
valid for whole curriculum period:
Prerequisites
valid for whole curriculum period:
FURTHER INFORMATION
Further Information
valid for whole curriculum period:
Teaching Language: English
Teaching Period: 2024-2025 Spring IV
2025-2026 Spring IVRegistration:
Registration for the course will take place on Sisu (sisu.aalto.fi). Maximum of 60 students will be accepted to the course with priority given to Master's Programme of Building Technology students. Other students can be selected based on motivation letter and/or other criteria.