Weekly Assignment V: Procurements (DL 9.12)
Completion requirements
Due: Thursday, 9 December 2021, 11:59 PM
- Work with your pair
- Your task is to categorize a sample of a general contractor’s suppliers (14 suppliers) according to Kraljik’s framework into a) bottleneck, b) strategic, c) non-critical and d) leverage suppliers
Data about suppliers’ deliveries in
the contractor’s projects is available in attached file
- Data consists of five variables: 1) suppliers (identification number), 2) project identification number, 3) number of orders in project, 4) total purchase amount (EUR) in project, and 4) a purchased item
- You have to use data to analyze suppliers according to supply risk and profit impact of their deliveries, to define supplier category for each supplier, and to justify your selection
Write a short word/pdf report of
your analysis and selections. You can use illustrative figures of your analysis
in the report.
Return in MyCourse
no later than 9.12.2021