CS-C2130 - Software Project 1, Lecture, 6.9.2023-1.12.2023
This course space end date is set to 01.12.2023 Search Courses: CS-C2130
Process Overview
(This document should give the Scrum Master, the Development team, the Product Owner, the Coach and other course personnel a common understanding on how the Scrum Team works.)
1. Project schedule and effort
start and end dates of all Sprints
allocated effort per person per Sprint
other main events such as project reviews
team work sessions at least for the current Sprint
Table 1. Sprint dates and allocated effort (an example)
Sprint | Dates | ScMa | Dev1 | ... | Dev6 | Comment |
Sprint 0 | 16.10.-7.11. | 25 | 40 | 40 | 40 | |
Sprint 1 | 8.11.-30.11. | 20 | 37 | 37 | 37 | |
break | 1.12.-3.1. | exam week & x-mas, no work | ||||
Sprint 2 | 4.1.-25.1. | 10 | 37 | 37 | 37 | |
Sprint 3 | 26.1.-27.2. | 10 | 37 | 37 | 37 | 12-16.2. exam week, no work |
Sprint 4 | 28.2-21.3. | 10 | 37 | 37 | 37 | |
Sprint 5 | 22.3.-15.4. | 20 | 37 | 37 | 37 | |
Total | 100h | 225h | 225h | 225h |
Table 2. Calendar (an example) (use e.g. Google Calendar and embed/link it here)
Date | Event and location |
20.10. 13-18 | Sprint 0 planning and Team work at Client |
21.10. 15-17 | Meeting with PO (Product vision) |
25.10. 15-20 | Team work at XX (project kick-off) |
26.10. 13-18 | Team work at XX (Meeting with the coach 17-18) |
5.11. 13-17 | Team work at XX |
5.11. 17-18 | Meeting with PO at XX |
... | |
7.11. 14-19 | Sprint 0-1 change |
... | Team work, meeting(s) with PO, ... |
29.11. 14-19 | Sprint 1-2 change |
30.11. 14-15 | Project Review 1 |
1.12. - 3.1. | X-mas break, no work or only some independent tasks alone |
4.1. | Team work, meeting(s) with PO, ... |
2. Recurring events of the Sprints
Concrete, short instructions (e.g. when, organizer & participants, how, results) for at least the following activities.
2.1 Sprint Planning
2.2 Sprint Review
2.3 Sprint Retrospective
2.4 "Daily” Scrums
2.5 Teamwork sessions
3. Other main practices and tools
Concrete, short instructions (e.g. when, by whom, how, results) for other main practices and tools.
3.1 Testing and other quality assurance practices
also link or embed Definition of Done here