(This document should give the Scrum Master, the Development team, the Product Owner, the Coach and other course personnel a common understanding on how the Scrum Team works.)

1. Project schedule and effort

  • start and end dates of all Sprints

  • allocated effort per person per Sprint

  • other main events such as project reviews

  • team work sessions at least for the current Sprint


Table 1. Sprint dates and allocated effort (an example)

Sprint

Dates

ScMa

Dev1

...

Dev6

Comment

Sprint 0

16.10.-7.11.

25

40

40

40


Sprint 1

8.11.-30.11.

20

37

37

37


break

1.12.-3.1.





exam week & x-mas, no work

Sprint 2

4.1.-25.1.

10

37

37

37


Sprint 3

26.1.-27.2.

10

37

37

37

12-16.2. exam week, no work

Sprint 4

28.2-21.3.

10

37

37

37


Sprint 5

22.3.-15.4.

20

37

37

37


Total


100h

225h

225h

225h



Table 2. Calendar (an example) (use e.g. Google Calendar and embed/link it here)

Date

Event and location

20.10. 13-18

Sprint 0 planning and Team work at Client

21.10. 15-17

Meeting with PO (Product vision)

25.10. 15-20

Team work at XX (project kick-off)

26.10. 13-18

Team work at XX (Meeting with the coach 17-18)

5.11. 13-17

Team work at XX

5.11. 17-18

Meeting with PO at XX

...


7.11. 14-19

Sprint 0-1 change

...

Team work, meeting(s) with PO, ...

29.11. 14-19

Sprint 1-2 change

30.11. 14-15

Project Review 1

1.12. - 3.1.

X-mas break, no work or only some independent tasks alone

4.1.

Team work, meeting(s) with PO, ...









2. Recurring events of the Sprints

Concrete, short instructions (e.g. when, organizer & participants, how, results) for at least the following activities.

2.1 Sprint Planning


2.2 Sprint Review


2.3 Sprint Retrospective


2.4 "Daily” Scrums


2.5 Teamwork sessions



3. Other main practices and tools

Concrete, short instructions (e.g. when, by whom, how, results) for other main practices and tools.


3.1 Testing and other quality assurance practices

  • also link or embed Definition of Done here

3.2 Communication channel(s)


3.3 Backlog management


3.4 Time tracking


3.5 Version control


3.6 Any other practices ...