MEC-E1003 - Machine Design Project, Lecture, 30.8.2023-1.12.2023
Kurssiasetusten perusteella kurssi on päättynyt 01.12.2023 Etsi kursseja: MEC-E1003
Milestones (click for details)
Week 35-36 |
Sept 8 |
|
Week 37 |
Sept 15 |
Design brief for group project |
Week 37-39 |
Sept 27-29 |
Stirling engine starter project (individual work) |
Week 40 |
Oct 6 |
Initial concept for group project |
Week 43 |
Oct 27 |
Concept pitch + peer review & 1st evaluation questionnaire |
Week 46 |
Nov 17 |
|
Week 47 |
|
Status report peer review |
Week 48 |
Nov 29 |
|
Week 48 |
Dec 1 |
Gala: Prototype demonstration & Demonstration gala reflections |
Week 50 |
Dec 15 |
Weeks 37-39
- Individually measure components of Stirling engine
- Select best ideas together as a group
- Operate engine in the lab and measure engine operation (Sept 27 or 29)
Already during weeks 37-39
- Initial ideation for your machine design project i.e., about functions, mechanism, its manufacturability etc.
- Select best ideas together as a group
Weeks 40-43: Develop concept and initial design
- Confirm concept to be developed (Oct 6)
- Decide components, materials (Granta Edupack), verify functionality (models, MBS), FEA (in critical places) and necessary steps of product design
- First draft of design documentation and manufacturing/ assembly plan
Week 43: Concept pitch in lieu of midterm exam (Oct 27)
- Pitch the concept, design process, material selection, manufacturing plan, assembly plan and other aspects (more details via announcement)
- Student groups are allowed to playback a pre-recorded concept pitch
- Peer review: Pre-determined groups will critique the concept pitches
- In case you have a time/order preference for the pitching session, please inform the course assistant beforehand
- Submit the 1st evaluation questionnaire (Oct 27)
Weeks 44-46: Detailed design & kickstart prototype development
- Iterate and further develop the machine concept design
- Update design documentation based on the detailed design
- Start updating and elaborating the manufacturing/ assembly plan & do a safety evaluation
- Project status report is a work-in-progress (draft) version of your final report (by Nov 17).
Include the progress/current status, schedule, work distribution, design documentation, draft versions of manufacturing, assembly and testing plans
- Submit the 2nd evaluation questionnaire (Nov 17)
Weeks 47-50: Exhibiting the prototype
- Status report peer review (week 47)
- Iterate prototype, finalize design documentation
- Advertising your project (poster for Gala by Nov 29)
- Gala presentation on Dec 1
- Complete demonstration gala reflections by midnight the day of the Gala
Week 51: Final reporting and Final evaluation questionnaire (by Dec 15)